Baltic Power, Hai Long and Oneida projects continue to make construction progress TORONTO, Nov. 13, 2024 (GLOBE NEWSWIRE) — Northland Power Inc. (“Northland” or the “Company”) (TSX: NPI) reported today financial results for the three and nine m
The Baltic Power project continues to make progress on fabrication of onshore and offshore substations, foundations, export cables, multiple turbine components and inter-array cables. This quarter marked the fabrication completion of the first sets of monopile foundations and transition pieces, which are ready to be delivered to the project. Construction of the onshore substation and the operations and management building are progressing. Major in-water construction activity is expected to start in early 2025. Full commercial operations are expected to commence in the latter half of 2026, according to schedule. Overall project cost is aligned with original expectations. Read More